early start date

The term Early Start Date is a project management term used in the context of the Critical Path Method

(CPM). The Early Start Date is the earliest possible time at which the incomplete parts of a schedule activity can begin. This date is determined by the schedule network

and all scheduleconstraints.

Unlike the Early Start Date, the Early Finish Date is the earliest possible time that the incomplete portions of a schedule activity can be completed according to the schedule network, date, and all schedule constraints.